Case Study: Overcoming Lead & Asbestos Abatement Scope Challenges

When the Division of General Services initiated the environmental remediation of the Stone Building at 67 Independence Drive, the project was scoped as a routine abatement of asbestos-containing building materials (ACBM) and lead paint. However, what began as a standard lead and asbestos abatement effort quickly became a far more complex operation requiring speed, scalability, and strategic decision-making under pressure.

The Problem: A Shift in Scope Without a Shift in Timeline

Lead paint embedded in building plaster.

Located in a multi-wing complex, the Stone Building spanned three floors in both the north and south wings (totaling 80,000 square feet), a 30,000-square-foot basement, and a four-story administrative wing. The plan was to remove all ACBM and lead-based paint, regardless of concentration, across the entire structure.

Initial site assessments suggested a conventional remediation process. But once abatement began, it became evident that the lead paint wasn’t just applied on the surface—it had been embedded in the underlying plaster throughout the building. This critical discovery forced a significant pivot: rather than simple surface treatment, full plaster removal was now required to ensure proper lead abatement.

The embedded lead paint fundamentally changed the scope of work. Complete plaster removal added layers of complexity, risk, and cost. But the most pressing concern was time.

Delays weren’t an option. The building’s renovation timeline was fixed, and pushing back milestones would create cascading impacts on future construction phases. The challenge was clear: complete a significantly larger job within the original schedule.

The Solution: Parke Environmental’s Rapid Response and Scalable Execution

Large hallway at the Stone House abatement project. 

Rather than pause the project or renegotiate terms, Parke Environmental assembled a 40-person team of highly trained abatement workers and supervisors and brought them on-site. Operations were immediately scaled up to run 24 hours a day, seven days a week, ensuring that progress continued without interruption.

To manage the increased scope, additional equipment, specialized tools, and logistical support were brought in. Supervisors worked with field teams to maintain quality control, ensure regulatory compliance, and monitor safety standards.

This rapid, decisive response allowed Parke Environmental to keep the project on track without compromising the integrity of the work.

Results That Reinforce Trust

Despite the expanded scope and tight timeline, the Parke Environmental delivered the completed project on schedule and to the client’s satisfaction. The success at 67 Independence Drive demonstrates more than technical skill—it highlights Parke Environmental’s ability to respond to complex challenges with agility, resourcefulness, and accountability.

Key Takeaways

The 67 Independence Drive project highlights Parke Environmental’s ability to adapt quickly, scale effectively, and deliver results under pressure. When unexpected conditions emerged, Parke Environmental didn’t hesitate to adjust the plan, mobilize a larger workforce, and maintain the original timeline—all without compromising quality or safety. This proactive, solutions-focused approach kept the project on track and reinforced the trust placed in us as a reliable partner capable of handling even the most complex abatement challenges.